Sputnik Opinion
In-depth analysis of regional & global events provided by Indian & foreign experts - from politics & economics to sci-tech & health.

Lessons To Be Learnt from Uttarakhand Tunnel Operation

© Photo : Social Media/ScreenshotTunnel
Tunnel - Sputnik India, 1920, 29.11.2023
Subscribe
All 41 workers were safely rescued from the incomplete Barkot-Silkyara tunnel after 400 hours - 17 days - on Tuesday evening. Sputnik India spoke with experts to discover why the rescue operation took so long.
On 12 November, after a landslide, the tunnel's 200-metre entrance was blocked with rocks, concrete stone, and metal, after which the Indian authorities launched a massive rescue operation.
However, authorities faced several challenges while drilling the remaining 60-meter stretch of rubble. As a result, the operation was delayed after the regular drilling machine broke and then the US auger machine was installed, however, on 24 November, its blade too broke beyond repair, finally, the debris was removed manually.

Challenges Faced By Authorities While Drilling

"The rescue operation at Himalayan is tricky. This is not a straightforward drill. The mountains are young, and if one tries to drill it forcefully, one may find an unknown water spring, which can flood or devastate the situation," C.P. Rajendran, geologist and Adjunct Professor at the National Institute of Advanced Studies, told Sputnik India.

As the machine keeps failing to do its job in the Himalayan region, the expert also said that there won't be more drilling with machines, they will look for alternate options.

".. You will not see the Augering anymore. Auger is finished. The drill (machine) has broken. It's irreparable. No more work from auger. No more drilling from the auger. There will not be a new drill," said tunneling expert Arnold Dix, who is especially called for the operation on Friday (November 24).

The final work was carried out manually, in which drilling is done by 'rat miner,' a method used to drill narrow shafts as part of a primitive method of coal extraction.

Volatile Ecology of the Himalayas

Professor C.P. Chandran opined that the Main Central Thrust (MCT) tectonic fault line along the Himalayas poses a risk to the construction of roads and tunnels in the region.

"The construction near areas like Silkyara tunnel which is close to the MCT fault line will always be risky," the professor said, adding, "rocks in the Himalayan region varied and had different strengths."

"Some rocks are soft, some are hard, creating stability issues in the region… This is not the first time we have seen such an incident. We are constantly witnessing disaster," Rajendran said.
The professor opined that before starting construction at volatile range, generally, geology and rock composition detailed examination should be done. Ignoring the region's geology could lead to dangerous accidents.

India Takes Action

"Government needs to learn lessons from the incident, and the whole project should emerge as a catalyst for a sustainable and harmonious coexistence between development and nature," Vimlendu Jha, an environmentalist & the founder of Swechha told Sputnik India.
The Silkyara tunnel is part of a $1.5bn, 890km-long Char Dham road project, which will connect four Hindu pilgrims, Badrinath, Kedarnath, Gangotri and Yamunotri in the Uttarakhand.
Following this incident, the National Highways Authority of India (NHAI) said that it will carry out a safety audit of 29 tunnels under construction tunnel, which includes 12 tunnels in the Himalayan state of Himachal Pradesh, six in the Jammu and Kashmir region, and the rest in other states including Uttarakhand.
Silkyara Tunnel  - Sputnik India, 1920, 28.11.2023
Political Affairs
Uttarakhand Tunnel Operation: All Workers Safely Rescued
Newsfeed
0
To participate in the discussion
log in or register
loader
Chats
Заголовок открываемого материала