Russia Completes Delivery of Reactor Safety Systems for India's Kudankulam Nuclear Plant Unit 3 & 4
Russia Completes Delivery of Reactor Safety Systems for India's Kudankulam Nuclear Plant Unit 3 & 4
Sputnik India
Russia’s state nuclear corporation, Rosatom, has completed the supply of advanced automated safety equipment for Units 3 and 4 of India’s Kudankulam Nuclear... 22.10.2026, Sputnik India
2026-10-22T14:28+0530
2026-10-22T14:28+0530
2026-10-22T14:28+0530
indo-russian relations
russia
india
rosatom
nuclear energy
nuclear power plant (npp)
https://cdn1.img.sputniknews.in/img/07e9/01/0f/8663311_0:158:2896:1787_1920x0_80_0_0_9d199573c56f39c84006e75f8010c586.jpg
Rosatom Automated Control Systems has completed delivery of the computerised subsystems of the Engineered Safety Features Actuation System (ESFAS CS) for Kudankulam Units 3 and 4, the Russian state nuclear corporation said in a statement.The delivery comprises around 300 pieces of equipment, with four independent sets allocated to each unit’s VVER-1000 reactor.Atomstroyexport, another Russian nuclear engineering company, serves as the project’s general designer and equipment supplier.The system continuously monitors reactor conditions, and if abnormal conditions arise, it automatically activates protective measures, including controlled cooldown of the reactor to bring it to a safe state.The design builds on the experience gained from the successful operation of Units 1 and 2, utilising non-programmable modules to improve resistance to common-cause failures.Installation at the plant will be followed by offline and integrated pre-commissioning tests.Kudankulam is planned to house six VVER-1000 reactors with a combined capacity of 6,000 MW. Units 1 and 2 are operational, while Units 3 and 4 remain under construction.
https://sputniknews.in/20260615/reactor-vessel-installed-at-unit-5-of-kudankulam-npp-in-india-rosatom-11261819.html
russia
india
Sputnik India
feedback.hindi@sputniknews.com
+74956456601
MIA „Rossiya Segodnya“
2026
Sangeeta Yadav
https://cdn1.img.sputniknews.in/img/07e6/0c/0f/110602_0:0:641:640_100x100_80_0_0_c298016a79eb02ef8caa9d1f688c12a5.jpg
Sangeeta Yadav
https://cdn1.img.sputniknews.in/img/07e6/0c/0f/110602_0:0:641:640_100x100_80_0_0_c298016a79eb02ef8caa9d1f688c12a5.jpg
News
en_IN
Sputnik India
feedback.hindi@sputniknews.com
+74956456601
MIA „Rossiya Segodnya“
https://cdn1.img.sputniknews.in/img/07e9/01/0f/8663311_152:0:2744:1944_1920x0_80_0_0_b766892c633d978592fcf082aee77b6c.jpgSputnik India
feedback.hindi@sputniknews.com
+74956456601
MIA „Rossiya Segodnya“
Sangeeta Yadav
https://cdn1.img.sputniknews.in/img/07e6/0c/0f/110602_0:0:641:640_100x100_80_0_0_c298016a79eb02ef8caa9d1f688c12a5.jpg
russia, india, rosatom, nuclear energy, nuclear power plant (npp)
russia, india, rosatom, nuclear energy, nuclear power plant (npp)
Russia Completes Delivery of Reactor Safety Systems for India's Kudankulam Nuclear Plant Unit 3 & 4
Russia’s state nuclear corporation, Rosatom, has completed the supply of advanced automated safety equipment for Units 3 and 4 of India’s Kudankulam Nuclear Power Plant in Tamil Nadu, marking another significant step in the construction of the VVER-1000 reactors.
Rosatom Automated Control Systems has completed delivery of the computerised subsystems of the Engineered Safety Features Actuation System (ESFAS CS) for Kudankulam Units 3 and 4, the Russian state nuclear corporation said in a statement.
The delivery comprises around 300 pieces of equipment, with four independent sets allocated to each unit’s VVER-1000 reactor.
Atomstroyexport, another Russian nuclear engineering company, serves as the project’s general designer and equipment supplier.
The system continuously monitors reactor conditions, and if abnormal conditions arise, it automatically activates protective measures, including controlled cooldown of the reactor to bring it to a safe state.
The design builds on the experience gained from the successful operation of Units 1 and 2, utilising non-programmable modules to improve resistance to common-cause failures.
Installation at the plant will be followed by offline and integrated pre-commissioning tests.
Kudankulam is planned to house six VVER-1000 reactors with a combined capacity of 6,000 MW. Units 1 and 2 are operational, while Units 3 and 4 remain under construction.